DIRECT ANSWERA turnaround replacement RFQ is scheduled backward from the site installation window through delivery, packing, final inspection, pressure test, fabrication, material receipt and drawing approval. Flag interfaces requiring shutdown measurement.
Backward schedule
- Outage and installation dates
- Transport and site-receipt lead time
- Inspection and dossier release
- Material, drawing and survey decision dates
Relevant manufacturing capability
- Drawing, datasheet and equipment-list manufacturability review
- Self-manufactured and coordinated-supply scope identification
- Technical, quality, document and delivery clarification
Key notes
- A promised shop completion date does not include site transport and installation readiness.