How Should Vessel Weld Repairs Be Controlled and Closed?

Close one traceable repair package per affected weld and incorporate it in the manufacturing dossier.

DIRECT ANSWERA weld repair begins with a located indication and approved disposition, then controlled removal, re-examination, qualified rewelding, any required heat treatment and final examination. Its history remains linked to the original joint and weld map.

Repair record fields

  • Joint and indication location with original NDE report
  • Defect extent and approved removal method
  • Repair WPS, personnel and cycle count
  • Re-NDE, heat treatment and final acceptance

Relevant manufacturing capability

  • Manufacturing-stage quality planning
  • Multi-method inspection and test coordination
  • Traceable release and manufacturing-dossier records

Key notes

  • Grinding an indication away without documented extent and reinspection does not close a repair.

FAQ

Frequently asked questions

01When may welding resume after defect removal?

After the prepared cavity is examined as required and the approved repair procedure, qualified personnel and inspection sequence are released.

RELATED

Related products and reference

PROJECT INQUIRY

Have a project? Send the drawings or technical conditions.

Send drawings, specifications, datasheets and design conditions for a manufacturability assessment based on the equipment type and project requirements.