How Should Process Design, Mechanical Design and Fabrication Responsibilities Be Split?

Create a responsibility matrix for each tag before bids are compared.

DIRECT ANSWERProcess design owns the service and governing operating/upset cases; mechanical design converts approved inputs into a pressure-boundary design; fabrication builds and verifies that approved design. Contract terms can reassign design work, but inputs, approvals and liability must be explicit.

Design-responsibility split

  • Process duty, relief and fluid properties
  • Mechanical calculations, materials and drawings
  • Fabrication methods, inspection and test
  • Change authority and final data handover

Relevant manufacturing capability

  • Drawing, datasheet and equipment-list manufacturability review
  • Self-manufactured and coordinated-supply scope identification
  • Technical, quality, document and delivery clarification

Key notes

  • A fabricator cannot responsibly infer missing process cases from the equipment name.

FAQ

Frequently asked questions

01If the vendor performs detailed design, who sets process conditions?

The buyer or designated process authority still supplies and approves governing process inputs unless the contract expressly assigns that task with adequate data.

RELATED

Related products and reference

PROJECT INQUIRY

Have a project? Send the drawings or technical conditions.

Send drawings, specifications, datasheets and design conditions for a manufacturability assessment based on the equipment type and project requirements.