Publish a mutually accepted inspection calendar before material receipt and fabrication.

DIRECT ANSWERThird-party inspection starts with an agreed ITP. Mark hold points that stop work until release, witness points that require timely notice, and record-review points; identify the inspector, notice period, acceptance document and missed-visit procedure.

Inspection interface

  • Activity and governing acceptance criterion
  • Hold, witness or review classification
  • Notice period and receiving party
  • Record, sign-off and release authority

Relevant manufacturing capability

  • Drawing, datasheet and equipment-list manufacturability review
  • Self-manufactured and coordinated-supply scope identification
  • Technical, quality, document and delivery clarification

Key notes

  • A missed inspection appointment does not automatically waive a contractual hold point.

FAQ

Frequently asked questions

01Can work continue if an inspector misses a witness point?

Follow the contract and approved ITP notification/waiver rule; a hold point still requires formal release.

RELATED

Related products and reference

PROJECT INQUIRY

Have a project? Send the drawings or technical conditions.

Send drawings, specifications, datasheets and design conditions for a manufacturability assessment based on the equipment type and project requirements.