What Lifting Inputs Must Be Frozen Before Large-Equipment Fabrication?

Approve a lift basis and identify which lifting attachments remain or are removed.

DIRECT ANSWERFreeze mass and centre of gravity, lifting points, lift orientation, shop workstations, rigging, temporary reinforcement, turnover, shipping and site receiving conditions before fabrication makes them hard to change.

Lifting design inputs

  • Operating, test and shipping weights
  • Centre of gravity and approved lift cases
  • Lugs/trunnions, rigging geometry and local loads
  • Shop turnover, transport and site crane interface

Relevant manufacturing capability

  • Large shell forming, fit-up and dimensional control
  • Sectional fabrication and heavy-equipment handling review
  • Inspection, documentation, lifting and transport coordination

Key notes

  • Crane rated capacity alone does not prove a lift is feasible.

FAQ

Frequently asked questions

01Who approves lifting points?

The design and project responsibility documents must assign calculation, review and approval.

RELATED

Related products and reference

PROJECT INQUIRY

Have a project? Send the drawings or technical conditions.

Send drawings, specifications, datasheets and design conditions for a manufacturability assessment based on the equipment type and project requirements.